Project Summary
The Florida Department of Transportation (FDOT) began a roadway project on June 12, 2024 along State Road (SR) 976/SW 40 Street/Bird Road from east of SW 87 Avenue to west of SW 58 Avenue.

WORK TO BE PERFORMED

  • Reconstructing sidewalks and upgrading pedestrian curb ramps
  • Installing a new traffic signal at SW 62 Avenue
  • Enhancing s pedestrian crosswalks at the following intersections: SW 84 Avenue, SW 82 Avenue, SW 79 Avenue, SW 7800 Block, SW 74 Avenue, SW 72 Avenue, SW 67 Avenue, SW 62 Avenue
  • Eliminating the left turn from southbound SW 60 Court to eastbound SW 40 Street
  • Eliminating the left turn from northbound SW 60 Court to westbound SW 40 Street
  • Eliminating the left turns from westbound SW 40 Street to southbound SW 59 Avenue and SW 62 Court
  • Modifying the concrete median at SW 61 Avenue to eliminate the through movement at the intersection
  • Upgrading vehicular and pedestrian signals, signage, and pavement markings
  • Extending the westbound SW 40 Street left turn lanes at SW 72 Avenue, SW 67 Avenue and SW 62 Avenue
  • Upgrading streetlights to Light-emitting Diode (LED)
  • Repaving and restriping the roadway

LANE CLOSURE INFORMATION
Travel lanes and sidewalks will be closed during non-peak hours on non-event days. Non-peak hours are:

Single Lane Closures

  • 9 a.m. to 3:30 p.m. weekdays and weekends
  • 7 p.m. to 6 a.m. weekdays and weekends

Double Lane Closures

  • 10 p.m. to 6 a.m. weekdays and weekends

DETOUR INFORMATION
Pedestrian and vehicular detours will be established at times and may exceed past the non-peak lane closures hours. Specific detour information will be provided before the corresponding construction activity is scheduled.
 

Project At-A-Glance
 
map
Start Date
June 2024

Est. Completion
Summer 2025

Construction Cost
$7.9 million

Lengths and Limits
SR 976/SW 40 Street/Bird Road from east of SW 87 Avenue to SW 58 Avenue

FDOT South Miami-Dade Resident Engineer
Dru Badri, P.E.

FDOT South Miami-Dade Assistant Resident Engineer
Jonathan Fundora, P.E.

FDOT Project Manager
Carmen Negron, P.E.

FDOT Project Administrator
Christopher Lopez

Community Outreach Specialist
Miranda Brito
Holt Communications, Inc.

O: (786) 837-4884
C: (786) 774-9714
Miranda.Brito@dot.state.fl.us.
 

×