Welcome
The Florida Department of Transportation (FDOT) is working on a roadway and resiliency project along State Road (SR) A1A/South Roosevelt Boulevard in Monroe County.
Please drive safely through the area as we complete final preparations for a traffic pattern and lane shift to the south side of the roadway.
WORK TO BE PERFORMED:
- Raising the roadway (up to 17.5 inches in some areas)
- Repairing and closing retaining wall gaps
- Installing a water pump station system and upgrading storm drainage for mitigation of tidal flooding
- Reconstructing the existing promenade along the south side of the roadway
- Adding some sidewalk along the north side of the roadway
- Upgrading curb ramps
- Installing three pedestrian crosswalks with Pedestrian Hybrid Beacons (PHBs)
- Repaving and restriping the roadway
- Installing new signage and pavement markings
LANE CLOSURE INFORMATION:
- Nighttime closure is planned starting Tuesday, May 21 from 9:30 p.m. to 5 a.m.
- Two travel lanes are temporarily closed, and travel is reduced to a single lane in each direction.
-
Additional lane closures will only be during non-peak hours on non-event days, nights, and weekends. Non-peak hours are:
- 9 a.m. to 4 p.m., Monday through Friday, and
- 9:30 p.m. to 5 a.m., Sunday through Thursday
- Access to adjacent residences and businesses will be maintained
- Parking is available in the lot on the north side of the road
- Crosswalks will allow for pedestrian access to the promenade and beach
- Minimum five foot pedestrian pathway will be maintained throughout the project
- Please be advised that temporary road closures may occur when heavy rains cause significant ponding on the roadway.
ALWAYS PUT SAFETY FIRST:
For your safety, and the safety of others, please use caution when driving, walking, or biking around any construction zone.
Project At-A-Glance
Start Date |
---|
January 2023 |
Est. Completion |
Spring 2025 |
Construction Cost |
$24.2 million |
Lengths and Limits |
Bertha St to End of Smathers Beach and Go Lane to SR 5/US 1/North Roosevelt Boulevard |
FDOT South Dade & Monroe Counties Resident Engineer |
Dru Badri, P.E. |
Construction Consulting Engineering and Inspection (CCEI) Project Manager |
Tony Sabbag, C.G.C., C.C.M. |
Construction Consulting Engineering and Inspection (CCEI) Senior Project Engineer |
Hector Rodriguez, M.S., P.E. H. Rodriguez Consulting Engineering, Inc. |
Contractor |
General Asphalt Company, LLC |
Community Outreach Specialist |
Julie Brown EXP US Services 305-923-1479 |